We are now three weeks into our installation at Glyn Cywarch and the project is starting to take shape.

The flow and return pipework between the EnergyBlade collectors and plant room is in and connected at both ends.

With the recent good weather, we have taken the opportunity to install the EnergyBlade collectors in the holding pools, which now need to be connected to their respective manifolds. The two manifolds will then be pressure tested again with the main flow and return to ensure quality.

Plantroom progress has been steady and all the equipment is now installed. All that remains is for some final insulation work and then electrical connections to be carried out. After that the two ground source heat pump units can be commissioned and the system left ready to connect to the central heating and hot water circuits.

Once completed 200kW of Ecoforest heat pump system will be used to supply energy to the stunning 17th century Grade II* listed house.